Named Phase 1 324 MW onshore wind east of Sunnyside (43–55 turbines, ~7.2 MW class) on ~4,600 ha Crown reserve, 138 kV customer-owned line to the hydrogen plant. EPR: behind-the-meter to electrolysis; NL Hydro grid power during low wind. Extra electricity desk. Not a merchant generator SKU in the EA; listed because the wind block is named and the census flags electricity. May produce with 2027–2030 build. CBSA 2716.00 electrical energy (T2026 ch.27). Not a fossil generator.